The City's annual street paving project is tentatively scheduled to begin the week of June 5th, weather permitting. The paving project will proceed in the following order:
Orange Tree Drive
North Country Club Drive (Glenbrook intersection to Troon Drive)
During the paving, equipment may temporarily impede access to properties and driveways on these streets for up to 20 minutes. Traffic lanes will be closed one lane at a time during the resurfacing. Flag personnel will be present to direct traffic.
Residents are asked to proceed with caution when traveling through the work area and be mindful of the workers.
Solid waste collection will maintain a normal schedule.